Thanks for registering for Structuring Gigawatts with Hans Royal and Christian Okoye. The recording is below, along with the full report we promised.

The Recording
Structuring Gigawatts: What speed-to-power is worth to AI data centers

Structuring-Gigawatts-Webinar-Slides.pdf

Structuring-Gigawatts-Webinar-Slides.pdf

323.41 KB • PDF File

Key Takeaways
A few numbers from the session

  • Compute is worth roughly $500/MWh for commodity inference and around $20,000/MWh at the frontier, according to the Compute Heat Rate.

  • On a 500 MW campus, each month of earlier power is worth roughly $200 million to nearly $1 billion.

  • Curtailing 100 MW for 30 hours a year over 10 years costs about $15M for self-hosted workloads and a few hundred million for frontier inference. Even then, about 9 months of faster interconnection pays for it.

  • No formal program yet guarantees faster interconnection in exchange for flexibility. ERCOT's PCLR is the closest.

Keep the Conversation Going
Work with Hans and Christian

The chat had more questions than we could answer live. Hans and Christian are happy to follow up directly.

Hans Royal

Hans and his team publish the Compute Heat Rate index and build custom analysis on top of it, from CHR for a specific region or model provider to research and commercial advisory for IPPs, powered land developers and colos. The Q4 index is out soon.

Christian Okoye

Occam Edge tracks which data center and power projects are actually getting built, and what that means for schedule and cost risk. They work with developers, investors and OEMs on behind-the-meter, around-the-meter and flexible builds.

DOTA by Integ

Book a DOTA demo, get a free pair of AirPods Pro.

DOTA is Integ's AI analytics and app builder for utilities and energy teams. Turn your operational data into validated, audit-ready apps without complicated IT workflows.

More Grid Innovation Hub sessions are coming before the end of the year and into 2027. We'll see you at the next one.

Best,
Adam Shaw
Grid Innovation Hub

Reply

Avatar

or to participate